This month, significant progress was made!
In my last update I expanded on the issues I was having with broken lag screws. This limited the progress made on the upper level. After considering the options available, I bit the bullet and moved from 1/4" to 5/16" lag screws. So now I have a lifetime supply of new 1/4" lag screws. Thanks Paul...I think!
In order to use to the new 5/16" screws, all of the stanchions had to have both mounting plate holes enlarged. It was back to the drill press to make the holes bigger. A lesson learned from using the 1/4" lag screws was to make the lower hole larger in order to enable lateral leveling. Now that I've moved to 5/16" lags, I have to expand both holes on the plates.
An interesting phenomenon happened while drilling the enlarged holes in the mounting plate. With nearly 90% of the drilling complete, I had a failure. A big failure. Something I had never experienced.

Yep, the chuck fell off! Talk about your oh sh!t moments! The drill bit was still intact in the chuck and still stuck in the mounting plate hole that was being drilled. This was further complicated by the fact that the bottom of the shaft is threaded in the center. Was there a bolt holding the chuck? Does a bolt or screw exist? Did I miss it? I certainly wasn't finding it on the ground.
Off to my desk and computer. I found the factory manual for the drill press. I was shocked that it was in the filing drawer. I purchased the drill press in 1994. A check of the parts diagram indicated that no bolt is used. Good news there!
Next was a visit to YouTube. There I found that the chuck is pressed onto the shaft. The shaft has a slight taper. I watched a few different videos to explore methods to reinstall the chuck to the shaft. I settled on using a mallet and a 2x4 to smack the chuck onto the shaft. I'm happy to report that this worked and I was back in business and drilling holes. I'm certainly glad I didn't have to replace the drill press!
Now, back to installing more stanchions. The next series of photos are different views of the progress as we filled 3 of 5 walls with stanchions.
In order to cross in front of the windows, I'll have a longer unsupported span of roughly 4'. My current plan is to rip plywood into 2"x48" sections that will be installed on end as stringers to support the sub-roadbed. I'm estimating that three sections per window will do the trick. I'll have the solution in place in my next update.
Extra time and thought was applied to the wall corners and the egress window (window to the right of the picture) in how the stanchions would be applied. For the corners, I need to have the appropriate support structure over a longer span. And, I want to avoid any vertical support post from the main level.
For the egress window, something that is easily removable yet still provides the support required for the removable portion of the upper level. I think I've settled on a solution. Stay tuned.
With 3+ walls of stanchions in place, it was time to start riser construction.
I managed to acquire some 15/32" OSB to use for the horizontal surface of the riser. Time to start ripping on the table saw. To the left is the result from four sheets of OSB.
In the background is my portable table saw. It's great, but the precision of the fence is sometimes questionable. It works well for this kind of work though.
Next up was to cut the risers to the needed lengths and then start cutting feet. All feet are 1 1/2" tall by 2" wide. I needed 200 feet be exact. The exception being 6 that are 3 1/2" for the risers on each end of the Santa Clara River bridge.
Here is the result. Not a terribly impressive stack!
Let the fun continue with the required gluing and clamping required to build the risers.
One round of risers built.
Now that the risers are built and the stanchions are up, riser installation can begin.
As previously mentioned, my goal is to keep the thickness of the upper level at 2 1/2". Given my construction, this is the minimum that I can achieve. The composition is as follows:
- 1" square tubing (stanchions)
- 17/32" space between the stanchion and the riser horizontal surface
- 15/32" OSB horizontal surface
- 1/2" drywall
Here is the first riser being placed. Risers are leveled front to back and side to side.
However, when we went to install the first riser, there was an issue. Because I'm keeping the deck so thin, The riser was hitting the lag screw on the stanchion mounting plate. Back to the chop saw to remedy the problem with 45-ish degree cuts.
Jason cut up some 17/32" hardwood spacers to use to block between the top of the stanchion and the bottom of the riser. His table saw is much better than mine. The proper clearance is achieved very quickly.
To the right are the spacers in action. They have saved us a ton of time in riser installation. Spacing is super fast. Risers are clamped quickly and aligned. We have a lot of lessons learned from main level riser installation.
Below is the first run of risers.
We found that the most effective way to install the risers while keeping everything level is to install the furthest two endpoints and then fill in the middle. The level is checked on both the front and the back. I'm very happy with the result. The 8' level is very handy!
And finally! The drywall installation started. We used the same method as before, Liquid Nails on on the riser horizontal surfaces, put the drywall down, and then add some drywall screws. On the first piece, we used two screws per riser. Probably overkill, but I want to make sure everything is solid.
With the first two pieces of drywall installed (16 feet of benchwork), we went back to riser installation. More risers were added. Unfortunately, I had to stop prior the span of the Santa Clara River. Apparently, I changed the spacing of the holes on the east stanchion when it was drilled. Oops! I used the 'regular' spacing standard for construction of the specific riser. Time to make a replacement riser.

One thing that was particularly important was to protect the track from 'falling objects' as the risers are installed. Clamps can come off as the riser legs are drawn to the steel with the mounting screw. Tools can fall. Especially the torpedo level. Ask me how I know. :)
I quickly grabbed a piece of scrap styrofoam to cover the rails while we worked. The pieces on hand have been used to protect the railroad, protect the window frames when bringing in 40"x20' sections of benchwork, etc. I'm glad I saved them from the rollaway tool box I purchased a number of years ago.
I also completed building the remaining electromagnets for remote uncoupling in the Violet Alley area. Below is a picture of the track plan. The alley tracks are 10 cars on one end and 14 on the other. The red X's represent where the electro magnets will be placed. Blue is the track, green is the backdrop.
In a blog post in December 2022, I elaborated on my plan for the electromagnets and the result of the testing. Having recently cut the steel for the electromagnets, I was ready to start building them.
To the right is a picture of the parts used:
- a spool of 24g magnet wire
- two 3/16" plates for the sides
- 1/4" washers for the core (18 washers)
- 1/4" bolt and nut
- Kapton tape to hold everything in place
With the parts ready, the next thing was to configure everything for spooling. I chucked the magnet in my drill. I mounted the spool of wire onto a screwdriver clamped to the benchwork. I used a clamp to keep the wire spool from coming off the screwdriver. The spooling of the magnet takes about 10 minutes, but seems to take forever. I used a drill to spin the magnet as I feed wire from the spool onto the electromagnet spool.
To the right is the finished product.That's a wrap for the May update. I expect to be laying upper level track in June.
Have a great summer!